Critical path method

Question: Critical path method
[A].

helps in ascertaining time schedules

[B].

makes better and detailed planning possible

[C].

provides a standard method for communicating project plans schedules and to time and cost performance

[D].

all of the above

Answer: Option D

Explanation:

No answer description available for this question.

Earliest finish time can be regarded as

Question: Earliest finish time can be regarded as
[A].

earliest start time + duration of activity

[B].

earliest start time – duration of activity

[C].

latest finish time + duration of activity

[D].

latest finish time – duration of activity

Answer: Option A

Explanation:

No answer description available for this question.