A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

Question: A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is
[A].

0.50

[B].

0.66

[C].

0.84

[D].

0.95

Answer: Option C

Explanation:

No answer description available for this question.

A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT).

Question: A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT).
[A].

Correct

[B].

Incorrect

Answer: Option A

Explanation:

No answer description available for this question.

Which of the following statement is correct about the network diagram?

Question: Which of the following statement is correct about the network diagram?
[A].

The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows.

[B].

The tail end of the arrow represents the start of an activity.

[C].

The head of the arrow represents the end of an activity.

[D].

all of the above

Answer: Option D

Explanation:

No answer description available for this question.