Our website is made possible by displaying online advertisements to our visitors. Please consider supporting us by whitelisting our website.

If 12 men work 8 hours a day to complete a work in 10 days, how many men working 12 hours a day can complete the work in 5 days?

If 12 men work 8 hours a day to complete a work in 10 days, how many men working 12 hours a day can complete the work in 5 days?

A. 16
B. 4
C. 12
D. 8
12 men work 8 hours for 10 days x men work 12 hours for 5 days x = (12*8*10)/(12*5) = 16 men