Question: Earliest finish time can be regarded as
[A].earliest start time + duration of activity
earliest start time – duration of activity
latest finish time + duration of activity
latest finish time – duration of activity
[A].
[B].
[C].
[D].
Answer: Option A
Explanation:
No answer description available for this question.