A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT).

Question: A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT).
[A].

Correct

[B].

Incorrect

Answer: Option A

Explanation:

No answer description available for this question.

Which of the following statement is correct about the network diagram?

Question: Which of the following statement is correct about the network diagram?
[A].

The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows.

[B].

The tail end of the arrow represents the start of an activity.

[C].

The head of the arrow represents the end of an activity.

[D].

all of the above

Answer: Option D

Explanation:

No answer description available for this question.

Critical path method

Question: Critical path method
[A].

helps in ascertaining time schedules

[B].

makes better and detailed planning possible

[C].

provides a standard method for communicating project plans schedules and to time and cost performance

[D].

all of the above

Answer: Option D

Explanation:

No answer description available for this question.