If daily wages of a man is double to that of a woman, how many men should work for 25 days to earn Rs.14400? Given that wages for 40 women for 30 days are Rs.21600.
A. 15
B. 14
C. 16
D. 13
A. 15
B. 14
C. 16
D. 13
A. 7 hour 15 minutes
B. 7 hour 30 minutes
C. 8 hour 15 minutes
D. 8 hour 30 minutes
Pages typed by Mansoor-Ul-Haque in 1 hour = 32/6 = 16/3
Pages typed by Aaqib in 1 hour = 40/5 = 8
Pages typed by Mansoor-Ul-Haque and Aaqib in 1 hour = 16/3 + 8 = 40/3
Time taken to type 110 pages when Mansoor-Ul-Haque and Aaqib work together = 110 × 3 /40 = 33/4
= 8 ¼ hours = 8 hour 15 minutes
A. 3 pm
B. 2 pm
C. 1:00 pm
D. 11 am
Work done by P in 1 hour = 1/8
Work done by Q in 1 hour = 1/10
Work done by R in 1 hour = 1/12
Work done by P,Q and R in 1 hour = 1/8 + 1/10 + 1/12 = 37/120
Work done by Q and R in 1 hour = 1/10 + 1/12 = 22/120 = 11/60
From 9 am to 11 am, all the machines were operating.
Ie, they all operated for 2 hours and work completed = 2 × (37/120) = 37/60
Pending work = 1- 37/60 = 23/60
Hours taken by Q an R to complete the pending work = (23/60) / (11/60) = 23/11
which is approximately equal to 2
Hence the work will be completed approximately 2 hours after 11 am ; ie around 1 pm
A. 8/15
B. 7/15
C. 11/15
D. 2/11
Amount of work P can do in 1 day = 1/15
Amount of work Q can do in 1 day = 1/20
Amount of work P and Q can do in 1 day = 1/15 + 1/20 = 7/60
Amount of work P and Q can together do in 4 days = 4 × (7/60) = 7/15
Fraction of work left = 1 – 7/15= 8/15
A. 30 min
B. 35 min
C. 40 min
D. 45 min
A. 40 days
B. 50 days
C. 60 days
D. 70 days
(A+B)’S 1 day’s work = [1/15−1/20]=1/60
A alone can finish it in 60 days
A. 50
B. 75
C. 60
D. 45
Part of work completed by Farjan and Kashif in a day
= 1/30 Part of work completed by them in 20 days
= 20/30 = 2/3 1/3 of the work is remaining. Kashif completes 1/3rd of the work in 25 days. Part of work completed by him in a day
= (1/3)÷25
= 1/75 (1/D)+(1/V) = 1/30 (1/D) = (1/30)-(1/75) = 1/50 Farjan can complete it in 50 days.
A. 12:00 pm
B. 2:00 am
C. 12:00 am
D. 10:00 pm
Jameel works for 5 hours. So he completes 5/15 = 1/3 of the task Nasir has to complete 2/3rd of the task 12*2/3 = 8 hours are needed. He completes the task at 12:00 am.
A. 10
B. 9
C. 11
D. 12
Work done by P in 1 day = 1/24
Work done by Q in 1 day = 1/9
Work done by R in 1 day = 1/12
Work done by Q and R in 1 day = 1/9 + 1/12 = 7/36
Work done by Q and R in 3 days = 3×7/36 = 7/12
Remaining work = 1 – 7/12 = 5/12
Number of days in which P can finish the remaining work = (5/12) / (1/24) = 10
A. 14
B. 16
C. 15
D. 11
Work done by Kamal in 1 day = 1/20
Work done by Suresh in 1 day = (1/20) × (125/100) = 5/80 = 1/16
=> Suresh can complete the work in 16 days