A. 24 days
B. 14 days
C. 15 days
D. 20 days
Time and Men are inversely proportional. Time taken by 28 men to finish the work = 15 days Time taken by a man to finish the work
= 15*28 days Time taken by 21 men = (15*28)/21 = 20 days
A. 24 days
B. 14 days
C. 15 days
D. 20 days
Time and Men are inversely proportional. Time taken by 28 men to finish the work = 15 days Time taken by a man to finish the work
= 15*28 days Time taken by 21 men = (15*28)/21 = 20 days
A. 10 days
B. 12 days
C. 8 days
D. 9 days
Part of work completed by C in 1 day = 1/12 Part of work completed by D in 1 day = 1/15 Part of work completed by C in 4 days
= 1/3 Work remaining = 2/3 Time taken by D to complete the work
= (2/3)÷(1/15) = 10 days
A. Rs.40
B. Rs.70
C. Rs.90
D. Rs.100
Amount Earned by P,Q and R in 1 day = 1620/9 = 180 —(1)
Amount Earned by P and R in 1 day = 600/5 = 120 —(2)
Amount Earned by Q and R in 1 day = 910/7 = 130 —(3)
(2)+(3)-(1) => Amount Earned by P , Q and 2R in 1 day
– Amount Earned by P,Q and R in 1 day = 120+130-180 = 70
=>Amount Earned by R in 1 day = 70
A. 5 days
B. 10 days
C. 15 days
D. 12 days
Work done by P in 1 day = 1/20
Work done by Q in 1 day = 1/12
Work done by P in 4 days = 4 × (1/20) = 1/5
Remaining work = 1 – 1/5 = 4/5
Work done by P and Q in 1 day = 1/20 + 1/12 = 8/60 = 2/15
Number of days P and Q take to complete the remaining work = (4/5) / (2/15) = 6
Total days = 4 + 6 = 10
A. 8
B. 6
C. 4
D. 2
Work done by P in 1 day = 1/18
Work done by Q in 1 day = 1/15
Work done by Q in 10 days = 10/15 = 2/3
Remaining work = 1 – 2/3 = 1/3
Number of days in which P can finish the remaining work = (1/3) / (1/18) = 6
A. 9(3/5) days
B. 9(1/5) days
C. 9(2/5) days
D. 10 days
Amount of work P can do in 1 day = 1/16
Amount of work Q can do in 1 day = 1/12
Amount of work P, Q and R can together do in 1 day = 1/4
Amount of work R can do in 1 day = 1/4 – (1/16 + 1/12) = 3/16 – 1/12 = 5/48
=> Hence R can do the job on 48/5 days = 9 (3/5) days
A. 12 hrs
B. 14 hrs
C. 16 hrs
D. 18 hrs
Explanation:
Part filled in 10 hrs.
= 10[1/15+1/20−1/25]=23/30
A. 12 days
B. 16 days
C. 18 days
D. 20 days
A. 85 days
B. 126 days
C. 118 days
D. 136 days
Time taken is inversely proportional to their efficiency. So, time taken is in the ratio 8:5. Time taken by Rashid to finish the work = 8x Time taken by Danish to finish the work = 5x 8x-5x=51 3x=51 x=17 8x=136
A. 16
B. 4
C. 12
D. 8
12 men work 8 hours for 10 days x men work 12 hours for 5 days x = (12*8*10)/(12*5) = 16 men