Generally PERT is preferred over CPM for the purpose of project evaluation.

Question: Generally PERT is preferred over CPM for the purpose of project evaluation.
[A].

Yes

[B].

No

Answer: Option A

Explanation:

No answer description available for this question.

Generally PERT is preferred over CPM for the purpose of project evaluation. Read More »

Industrial Engineering And Production Management, Mechanical Engineering

Critical path method

Question: Critical path method
[A].

helps in ascertaining time schedules

[B].

makes better and detailed planning possible

[C].

provides a standard method for communicating project plans schedules and to time and cost performance

[D].

all of the above

Answer: Option D

Explanation:

No answer description available for this question.

Critical path method Read More »

Industrial Engineering And Production Management, Mechanical Engineering

Earliest finish time can be regarded as

Question: Earliest finish time can be regarded as
[A].

earliest start time + duration of activity

[B].

earliest start time – duration of activity

[C].

latest finish time + duration of activity

[D].

latest finish time – duration of activity

Answer: Option A

Explanation:

No answer description available for this question.

Earliest finish time can be regarded as Read More »