A. 0.6 Hs and 1.67 Hs
B. 0.6 Hs and 1.87 Hs
C. 1.27 Hs and 1.87 Hs
D. 1.27 Hs and 1.67 Hs
A. 0.6 Hs and 1.67 Hs
B. 0.6 Hs and 1.87 Hs
C. 1.27 Hs and 1.87 Hs
D. 1.27 Hs and 1.67 Hs
Select your answer based on the coding system given below.
A. Both A and R are true and R is the correct explanation of A.
B. Both A and R are true but R is not correct explanation of A.
C. A is true but R is false.
D. A is false but R is true.
(i) The Beaufort number ranges from 1 to 12.
(ii) Higher Beaufort number indicates higher speed of wind,
(iii) Beaufort number for calm is smallest and for hurricane is highest
select the correct statments.
A. (i) and (ii) are correct
B. (ii) and (iii) are correct
C. (i) and (iii) are correct
D. (i), (ii) and (iii) are correct
i) varies with latitude and season
ii) is more than displacement tonnage
iii) is the difference between displacement load and displacement light
select the correct statemens.
A. i) and ii) are correct
B. ii) and iii) are correct
C. i) and iii) are correct
D. Only iii) is correct
(i) loaded draft + 1.2 m when bottom is rock
(ii) loaded draft + 1.8 m when bottom is soft
(iii) loaded draft + 1.2 m when bottom is soft
(iv) loaded draft + 1.8 m when bottom is rock
select the correct the correct statements.
A. (i) and (ii) are correct
B. (i) and (iii) are correct
C. (ii) and (iv) are correct
D. (iii) and (iv) are correct
Select your answer based on the coding system given below.
A. Both A and R are true and R is the correct explanation of A.
B. Both A and R are true but R is not the correct explanation of A.
C. A is true but R is false.
D. A is false but R is true.
A. the length of design vessel
B. the length of design vessel + 10% clearance between adjacent vessels
C. the length of design vessel + 20% clearance between adjacent vessels
D. twice the length of design vessel
A. 1.3412
B. 1.5612
C. 1.7412
D. 1.9412
where ‘t’ is the period in seconds for two successive waves to pass the same section
A. Manoeuvring lane + 2 x Bank clearance lane
B. 2 x Manoeuvring lane + 2 x Bank clearance lane
C. 2 x Manoeuvring lane + 2 x Bank clearance lane + ship clearance lane
D. Manoeuvring lane + 2 x Bank clearance lane + ship clearance lane
A. The progress of work in low level method of mound construction is very slow.
B. Barge method of mound construction is economical.
C. In low level method of mound construction, the area of working is limited.
D. In staging method of mound cons-truction, the work is not interrupted even during stormy weather