Our website is made possible by displaying online advertisements to our visitors. Please consider supporting us by whitelisting our website.

Basic Maths Mcqs

Efficiency of Rashid and Danish are in the ratio 5:8. If Danish takes 51 days less than Rashid to complete the work, find the time taken by Rashid to complete the work.

Efficiency of Rashid and Danish are in the ratio 5:8. If Danish takes 51 days less than Rashid to complete the work, find the time taken by Rashid to complete the work.

A. 85 days
B. 126 days
C. 118 days
D. 136 days
Time taken is inversely proportional to their efficiency. So, time taken is in the ratio 8:5. Time taken by Rashid to finish the work = 8x Time taken by Danish to finish the work = 5x 8x-5x=51 3x=51 x=17 8x=136

Efficiency of Rashid and Danish are in the ratio 5:8. If Danish takes 51 days less than Rashid to complete the work, find the time taken by Rashid to complete the work. Read More »

Basic Maths Mcqs, Mathematics Mcqs, Time and Work Mcqs

If 12 men work 8 hours a day to complete a work in 10 days, how many men working 12 hours a day can complete the work in 5 days?

If 12 men work 8 hours a day to complete a work in 10 days, how many men working 12 hours a day can complete the work in 5 days?

A. 16
B. 4
C. 12
D. 8
12 men work 8 hours for 10 days x men work 12 hours for 5 days x = (12*8*10)/(12*5) = 16 men

If 12 men work 8 hours a day to complete a work in 10 days, how many men working 12 hours a day can complete the work in 5 days? Read More »

Basic Maths Mcqs, Mathematics Mcqs, Time and Work Mcqs

If daily wages of a man is double to that of a woman, how many men should work for 25 days to earn Rs.14400? Given that wages for 40 women for 30 days are Rs.21600.

If daily wages of a man is double to that of a woman, how many men should work for 25 days to earn Rs.14400? Given that wages for 40 women for 30 days are Rs.21600.

A. 15
B. 14
C. 16
D. 13

If daily wages of a man is double to that of a woman, how many men should work for 25 days to earn Rs.14400? Given that wages for 40 women for 30 days are Rs.21600. Read More »

Basic Maths Mcqs, Mathematics Mcqs, Time and Work Mcqs

Mansoor-Ul-Haque and Aaqib are working on a special assignment. Mansoor-Ul-Haque needs 6 hours to type 32 pages on a computer and Aaqib needs 5 hours to type 40 pages. If both of them work together on two different computers, how much time is needed to type an assignment of 110 pages?

Mansoor-Ul-Haque and Aaqib are working on a special assignment. Mansoor-Ul-Haque needs 6 hours to type 32 pages on a computer and Aaqib needs 5 hours to type 40 pages. If both of them work together on two different computers, how much time is needed to type an assignment of 110 pages?

A. 7 hour 15 minutes
B. 7 hour 30 minutes
C. 8 hour 15 minutes
D. 8 hour 30 minutes
Pages typed by Mansoor-Ul-Haque in 1 hour = 32/6 = 16/3
Pages typed by Aaqib in 1 hour = 40/5 = 8
Pages typed by Mansoor-Ul-Haque and Aaqib in 1 hour = 16/3 + 8 = 40/3
Time taken to type 110 pages when Mansoor-Ul-Haque and Aaqib work together = 110 × 3 /40 = 33/4
= 8 ¼ hours = 8 hour 15 minutes

Mansoor-Ul-Haque and Aaqib are working on a special assignment. Mansoor-Ul-Haque needs 6 hours to type 32 pages on a computer and Aaqib needs 5 hours to type 40 pages. If both of them work together on two different computers, how much time is needed to type an assignment of 110 pages? Read More »

Basic Maths Mcqs, Mathematics Mcqs, Time and Work Mcqs

Machine P can print one lakh books in 8 hours. Machine Q can print the same number of books in 10 hours while machine R can print the same in 12 hours. All the machines started printing at 9 A.M. Machine P is stopped at 11 A.M. and the remaining two machines complete work. Approximately at what time will the printing of one lakh books be completed?

Machine P can print one lakh books in 8 hours. Machine Q can print the same number of books in 10 hours while machine R can print the same in 12 hours. All the machines started printing at 9 A.M. Machine P is stopped at 11 A.M. and the remaining two machines complete work. Approximately at what time will the printing of one lakh books be completed?

A. 3 pm
B. 2 pm
C. 1:00 pm
D. 11 am
Work done by P in 1 hour = 1/8
Work done by Q in 1 hour = 1/10
Work done by R in 1 hour = 1/12
Work done by P,Q and R in 1 hour = 1/8 + 1/10 + 1/12 = 37/120
Work done by Q and R in 1 hour = 1/10 + 1/12 = 22/120 = 11/60
From 9 am to 11 am, all the machines were operating.
Ie, they all operated for 2 hours and work completed = 2 × (37/120) = 37/60
Pending work = 1- 37/60 = 23/60
Hours taken by Q an R to complete the pending work = (23/60) / (11/60) = 23/11
which is approximately equal to 2
Hence the work will be completed approximately 2 hours after 11 am ; ie around 1 pm

Machine P can print one lakh books in 8 hours. Machine Q can print the same number of books in 10 hours while machine R can print the same in 12 hours. All the machines started printing at 9 A.M. Machine P is stopped at 11 A.M. and the remaining two machines complete work. Approximately at what time will the printing of one lakh books be completed? Read More »

Basic Maths Mcqs, Mathematics Mcqs, Time and Work Mcqs

P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work together for 4 days, what is the fraction of work left?

P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work together for 4 days, what is the fraction of work left?

A. 8/15
B. 7/15
C. 11/15
D. 2/11
Amount of work P can do in 1 day = 1/15
Amount of work Q can do in 1 day = 1/20
Amount of work P and Q can do in 1 day = 1/15 + 1/20 = 7/60
Amount of work P and Q can together do in 4 days = 4 × (7/60) = 7/15
Fraction of work left = 1 – 7/15= 8/15

P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work together for 4 days, what is the fraction of work left? Read More »

Basic Maths Mcqs, Mathematics Mcqs, Time and Work Mcqs

Two pipes P and Q can fill a cistern in 12 min. and 15 min. respectively but a third pipe ‘R’ can empty the full tank in 6 min.  P and Q are kept open for 5 min. in the beginning and then ‘R’ is also opened.  In what time is the cistern emptied ?

Two pipes P and Q can fill a cistern in 12 min. and 15 min. respectively but a third pipe ‘R’ can empty the full tank in 6 min.  P and Q are kept open for 5 min. in the beginning and then ‘R’ is also opened.  In what time is the cistern emptied ?

A. 30 min
B. 35 min
C. 40 min
D. 45 min

Two pipes P and Q can fill a cistern in 12 min. and 15 min. respectively but a third pipe ‘R’ can empty the full tank in 6 min.  P and Q are kept open for 5 min. in the beginning and then ‘R’ is also opened.  In what time is the cistern emptied ? Read More »

Basic Maths Mcqs, Mathematics Mcqs, Time and Work Mcqs

A and B can together do a piece of work in 15 days. B alone can do it in 20 days. In how many days can A alone do it ?

A and B can together do a piece of work in 15 days. B alone can do it in 20 days. In how many days can A alone do it ?

A. 40 days
B. 50 days
C. 60 days
D. 70 days
(A+B)’S 1 day’s work = [1/15−1/20]=1/60
A alone can finish it in 60 days

A and B can together do a piece of work in 15 days. B alone can do it in 20 days. In how many days can A alone do it ? Read More »

Basic Maths Mcqs, Mathematics Mcqs, Time and Work Mcqs

Farjan and Kashif can complete a task in 30 days. Farjan leaves after 20 days and Kashif alone completes it in another 25 days. How many days does Farjan alone take to complete the entire task?

Farjan and Kashif can complete a task in 30 days. Farjan leaves after 20 days and Kashif alone completes it in another 25 days. How many days does Farjan alone take to complete the entire task?

A. 50
B. 75
C. 60
D. 45
Part of work completed by Farjan and Kashif in a day
= 1/30 Part of work completed by them in 20 days
= 20/30 = 2/3 1/3 of the work is remaining. Kashif completes 1/3rd of the work in 25 days. Part of work completed by him in a day
= (1/3)÷25
= 1/75 (1/D)+(1/V) = 1/30 (1/D) = (1/30)-(1/75) = 1/50 Farjan can complete it in 50 days.

Farjan and Kashif can complete a task in 30 days. Farjan leaves after 20 days and Kashif alone completes it in another 25 days. How many days does Farjan alone take to complete the entire task? Read More »

Basic Maths Mcqs, Mathematics Mcqs, Time and Work Mcqs

Jameel can complete a task in 15 hours and Nasir can complete the same task in 12 hours. Jameel starts the task at 9:00 am and stops working at 2:00pm. Nasir starts working on the task at 4:00 pm. At what time is the task completed?

Jameel can complete a task in 15 hours and Nasir can complete the same task in 12 hours. Jameel starts the task at 9:00 am and stops working at 2:00pm. Nasir starts working on the task at 4:00 pm. At what time is the task completed?

A. 12:00 pm
B. 2:00 am
C. 12:00 am
D. 10:00 pm
Jameel works for 5 hours. So he completes 5/15 = 1/3 of the task Nasir has to complete 2/3rd of the task 12*2/3 = 8 hours are needed. He completes the task at 12:00 am.

Jameel can complete a task in 15 hours and Nasir can complete the same task in 12 hours. Jameel starts the task at 9:00 am and stops working at 2:00pm. Nasir starts working on the task at 4:00 pm. At what time is the task completed? Read More »

Basic Maths Mcqs, Mathematics Mcqs, Time and Work Mcqs