A dummy activity is used in PERT network to describe the_____________________?
A. Precedence relationship
B. Resource idleness
C. Resource restriction
D. Necessary time delay
A. Precedence relationship
B. Resource idleness
C. Resource restriction
D. Necessary time delay
[B].
[C].
[D].
Answer: Option B
Explanation:
No answer description available for this question.
A. Outside
B. Inside
C. Mean
D. None of these
[B].
[C].
[D].
Answer: Option A
Explanation:
No answer description available for this question.
[B].
[C].
[D].
Answer: Option A
Explanation:
No answer description available for this question.
[B].
[C].
[D].
Answer: Option A
Explanation:
No answer description available for this question.
[B].
[C].
[D].
Answer: Option D
Explanation:
No answer description available for this question.