A can do a particular work in 6 days . B can do the same work in 8 days. A and B signed to do it for Rs. 3200. They completed the work in 3 days with the help of C. How much is to be paid to C?

A can do a particular work in 6 days . B can do the same work in 8 days. A and B signed to do it for Rs. 3200. They completed the work in 3 days with the help of C. How much is to be paid to C?

A. Rs. 380
B. Rs. 600
C. Rs. 420
D. Rs. 400
Amount of work A can do in 1 day = 1/6
Amount of work B can do in 1 day = 1/8
Amount of work A + B can do in 1 day = 1/6 + 1/8 = 7/24
Amount of work A + B + C can do = 1/3
Amount of work C can do in 1 day = 1/3 – 7/24 = 1/24
work A can do in 1 day: work B can do in 1 day: work C can do in 1 day
= 1/6 : 1/8 : 1/24 = 4 : 3 : 1
Amount to be paid to C = 3200 × (1/8) = 400