A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

Question: A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is
[A].

0.50

[B].

0.66

[C].

0.84

[D].

0.95

Answer: Option C

Explanation:

No answer description available for this question.