A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT).

Question: A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT).
[A].

Correct

[B].

Incorrect

Answer: Option A

Explanation:

No answer description available for this question.