Question:
With reference to project management, identify which of the following statement is NOT correct?
| A. |
Gantt chart is a principal tool used in scheduling and also in some methods of loading. |
B. |
Routing is the first step in the production planning. |
C. |
The cost of any activity is proportional to its time of completion. |
D. |
The free float can be calculated by subtracting EFT from EST. |
Answer» d. The free float can be calculated by subtracting EFT from EST. |
Note: |
The above multiple-choice question is for all general and Competitive Exams in India. |