Which one of the following is not an excavating and moving type of equipment ?
A. Bulldozer
B. Clam shell
C. Scraper
D. Dump truck
A. Bulldozer
B. Clam shell
C. Scraper
D. Dump truck
A. increase in rates of only important materials
B. variation in cost in materials element, labour element and petrol-oil-lubricant element
C. variation in total cost of the project on an ad hoc basis
D. rate of inflation
A. greater than or equal to latest event time of preceding node
B. less than or equal to latest event time of preceding node
C. equal to latest event time of preceding node
D. less than latest event time of preceding node
A. change of critical path
B. decrease of project completion time
C. increase of project completion time
D. all of the above
A. Rs. 8,43,750/-
B. Rs. 8,75,000/-
C. Rs. 10,50,000/-
D. Rs. 11,56,250/-
A. Hoe
B. Shovel
C. Dragline
D. None of the above
Consider the following operations :
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
A. 1,2,4,3,5
B. 1,3,2,4,5
C. 1,2,3,4,5
D. 1,3,4,2,5