Which of the following states that work expands to fill the time available ?

Which of the following states that work expands to fill the time available ?

A. CASE tools
B. Pricing to win
C. Parkinson’s Law
D. Expert judgement

Explanation: The cost is determined by available resources rather than by objective assessment. If the software has to be delivered in 12 months and 5 people are available, the effort required is estimated to be 60 person-months.