Which of the following is a systematic attempt to specify threats to the project plan ?
A. Risk identification
B. Performance risk
C. Support risk
D. Risk projection
Explanation: By identifying known and predictable risks, the project manager takes a first step toward avoiding them when possible and controlling them when necessary.