The process of transforming a model into source code is known as___________________?
		A. Forward engineering
B. Reverse engineering
C. Re-engineering
D. Reconstructing
		A. Forward engineering
B. Reverse engineering
C. Re-engineering
D. Reconstructing
		A. Introducing new practices, methods or processes
B. Introducing new team members to existing project
C. Introducing or removing deliverable
D. Introducing new roles or responsibilities
Explanation: Adding more developers aid to process completion rather than changing it.
		A. Process measurement
B. Process analysis
C. Process change
D. None of the mentioned
Explanation: In Process analysis the current process is assessed and bottlenecks and weaknesses are identified.
		A. Ul 1998, Second Edition
B. UT 1998, Second Edition
C. Ul 1992, Second Edition
D. Ul 1996, Second Edition
		A. rework
B. repair
C. failure mode analysis
D. none of the mentioned
Explanation: Failure costs are those that would disappear if no defects appeared before shipg a product to customers.
		A. Beginner’s Guide
B. Installation guide
C. Reference Guide
D. SRS
Explanation: SRS provides information on exact requirements of system as agreed between user and developers.
		A. CMM
B. ISO 9001
C. ISO 9000-3
D. None of the mentioned
Explanation: ISO 9000-3 states that the supplier should carry out reviews to ensure the requirements are met and design methods are correctly carried out.