The load factor of domestic load is usually____________?
A. 10 to 15%
B. 30 to 40%
C. 50 to 60%
D. 60 to 70%
A. 10 to 15%
B. 30 to 40%
C. 50 to 60%
D. 60 to 70%
A. the capital cost divided by number of year of life
B. the capital cost minus the salvage value, is divided by the number of years of life
C. increasing a uniform sum of money per annum at stipulated rate of interest
D. none of the above
A. Nuclear power plant
B. Hydro-electric power plants
C. Thermal power plants
D. Diesel engine power plants
A. Nuclear power plant
B. Steam turbine plant
C. Pumped storage plant
D. None of the above
A. Hot reserve
B. Cold reserve
C. Sning reserve
D. Firm power
A. operating schedule of generating units
B. sizes of generating units
C. total installed capacity of the plant
D. all of the above
A. plant is used for stand by purpose only
B. plant is under maintenance
C. plant is used for base load only
D. plant is used for peak load as well as base load