The constraints in case of resource smoothening operation would be_______________?
A. resources
B. project duration time
C. both resources and project duration time
D. none of the above
A. resources
B. project duration time
C. both resources and project duration time
D. none of the above
A. Concrete
B. Loose sand
C. Asphalt
D. Firm earth
A. on commencement of work at site for payment of loan taken by him
B. for the purchase of construction materials
C. for the payment of advances to labour and other staff
D. for all activities required to start the work at site on finalization of the contract document
A. 2.3% and 84.1%
B. 97.7% and 84.1%
C. 97.7 % and 15.9%
D. 15.9% and 97.7%
A. Kneading
B. Pressing
C. Tamg
D. Vibration
A. greater than or equal to latest event time of preceding node
B. less than or equal to latest event time of preceding node
C. equal to latest event time of preceding node
D. less than latest event time of preceding node
A. Rs. 8,43,750/-
B. Rs. 8,75,000/-
C. Rs. 10,50,000/-
D. Rs. 11,56,250/-