[A].
[B].
[C].
[D].
Answer: Option A
Explanation:
Ratio of rates of working of A and B = 2 : 1.
So, ratio of times taken = 1 : 2.
| B’s 1 day’s work = | 1 | . |
| 12 |
| A’s 1 day’s work = | 1 | ; (2 times of B’s work) |
| 6 |
| (A + B)’s 1 day’s work = | 1 | + | 1 | = | 3 | = | 1 | . | ||
| 6 | 12 | 12 | 4 |
So, A and B together can finish the work in 4 days.