With reference to project management, identify which of the following statement is NOT correct?

Question:

With reference to project management, identify which of the following statement is NOT correct?

A.

Gantt chart is a principal tool used in scheduling and also in some methods of loading.

B.

Routing is the first step in the production planning.

C.

The cost of any activity is proportional to its time of completion.

D.

The free float can be calculated by subtracting EFT from EST.

Answer» d. The free float can be calculated by subtracting EFT from EST.

Note: The above multiple-choice question is for all general and Competitive Exams in India

Which of the following function does money serve when used to measure the prices of different goodsand services?

Question:

Which of the following function does money serve when used to measure the prices of different goodsand services?

A.

Store of value

B.

Medium of exchange

C.

Standard of value

D.

Display of power

Answer» c. Standard of value

Note: The above multiple-choice question is for all general and Competitive Exams in India

Which one of the following standards is associated with the “Quality Assurance in FinalInspection Test”?

Question:

Which one of the following standards is associated with the “Quality Assurance in FinalInspection Test”?

A.

ISO 9001

B.

ISO 9002

C.

ISO 9003

D.

ISO 9004

Answer» c. ISO 9003

Note: The above multiple-choice question is for all general and Competitive Exams in India