Question:
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
[A].
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
[A].
5 | 5 |
11 |
[B].
5 | 6 |
11 |
[C].
6 | 5 |
11 |
[D].
6 | 6 |
11 |
Answer: Option A
Explanation:
P can complete the work in (12 x 8) hrs. = 96 hrs.
Q can complete the work in (8 x 10) hrs. = 80 hrs.
P’s1 hour’s work = | 1 | and Q’s 1 hour’s work = | 1 | . |
96 | 80 |
(P + Q)’s 1 hour’s work = | 1 | + | 1 | = | 11 | . | ||
96 | 80 | 480 |
So, both P and Q will finish the work in | 480 | hrs. | ||
11 |
Number of days of 8 hours each = | 480 | x | 1 | = | 60 | days = 5 | 5 | days. | ||
11 | 8 | 11 | 11 |