Interfering float is the difference between__________________?
A. total float and free float
B. total float and independent float
C. free float and independent float
D. none of the above
A. total float and free float
B. total float and independent float
C. free float and independent float
D. none of the above
A. Moist loam
B. Sand and gravel
C. Good common earth
D. Wet sticky clay
A. on all the activities
B. on all the activities lying on the critical path
C. only on activities lying on the orginal critical path and having flatter cost slopes
D. on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
A. normal durations for all the activities
B. crash durations for all activities
C. crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
D. crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
A. total float
B. free float
C. interfering float
D. independent float
Consider the following features/factors
1. Projects are of the non-repetitive type.
2. Time required need not be known.
3. Time required is known precisely.
4. Events have been established for planning.
5. Emphasis is given to activities of project
A. 1,2 and 4
B. 3,4 and 5
C. 1,3 and 4
D. 1,2 and 5
A. 8 days
B. 9 days
C. 10 days
D. 15 days