In “full face” method of constructing tunnels, the first operation relates to______________?
A. removal of bottom portion
B. excavation of one drift in the centre
C. removal of top portion
D. excavation being done along the periphery
A. removal of bottom portion
B. excavation of one drift in the centre
C. removal of top portion
D. excavation being done along the periphery
1. drilling and blasting
2. timbering
3. pumg
4. mucking
Select the correct answer using the codes given below Codes?
A. 1,2,3,4
B. 1,4,2,3
C. 2,1,4,3
D. 2,4,1,3
A. 42 D
B. 82 D
C. 104 D
D. 124 D
A. 6 mJ per second per m2 of face area
B. 6 m3 per minute per m2 of face area
C. 20 m3 per minute per m2 of face area
D. 6 m3 per hour per m2 of face area
A. Both A and R are true and R is the correct explanation of A
B. Both A and R are true but R is not the correct explanation of A
C. A is true but R is false
D. A is false but R is true
A. 2 m
B. 3 m
C. 4 m
D. 5 m
A. carrying water
B. non-cohesive soils
C. tunnels driven by shield method
D. placement of concrete lining