If the risk of a flood occurring in the next 10 years is accepted to 10%, then the return period for design should be__________________?

If the risk of a flood occurring in the next 10 years is accepted to 10%, then the return period for design should be__________________?

A. 1 + (0.9)010
B. 1 – (0.9)°l0
C. 1/(1-0.9°10)
D. 1/(1+ 0.9010)