If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively___________________?
A. 3.5 and 5/6
B. 5 and 25/36
C. 3.5 and 25/36
D. 4 and 5/6
A. 3.5 and 5/6
B. 5 and 25/36
C. 3.5 and 25/36
D. 4 and 5/6
A. expected time of activity A is greater than the expected time of activity B
B. expected time of activity B is greater than the expected time of activity A
C. expected time of both activities A and B are same
D. none of the above
A. should invest in neither of the two projects
B. could invest in either of the two projects
C. should invest in project A
D. should invest in project B
A. most likely time
B. optimistic time
C. pessimistic time
D. expected time
A. total float
B. free float
C. interfering float
D. independent float
A. 2.3% and 84.1%
B. 97.7% and 84.1%
C. 97.7 % and 15.9%
D. 15.9% and 97.7%
A. greater than earliest event time of the following node
B. less than earliest event time of the following node
C. less than or equal to earliest event time of the following node
D. greater than or equal to earliest event time of the following node