Question:
If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
[A].4 days
5 days
6 days
7 days
If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
[A].
[B].
[C].
[D].
Answer: Option A
Explanation:
Let 1 man’s 1 day’s work = x and 1 boy’s 1 day’s work = y.
Then, 6x + 8y = | 1 | and 26x + 48y = | 1 | . |
10 | 2 |
Solving these two equations, we get : x = | 1 | and y = | 1 | . |
100 | 200 |
(15 men + 20 boy)’s 1 day’s work = | 15 | + | 20 | = | 1 | . | ||
100 | 200 | 4 |
15 men and 20 boys can do the work in 4 days.