For laying a sewer line in a trench of 2 m width, an offset line is marked on the ground parallel to the given centre line at a distance of___________________?
A. 100 cm
B. 120 cm
C. 140 cm
D. 160 cm
A. 100 cm
B. 120 cm
C. 140 cm
D. 160 cm
A. Oxygen
B. Nitrogen
C. Hydrogen
D. Carbon dioxide
A. 2.4 m
B. 3.0 m
C. 4.0 m
D.”2.5 m
E. 5.0 m
A. It is cheaper in construction
B. It provides maximum area for a given perimeter
C. It provides maximum hydraulic mean depth
D. All the above
A. 900 minutes
B. 4 minutes
C. 4 x (225)3/2 minutes
D. 4 (225)1/3 minutes
E. 4 x V225 minutes
A. More than the self-cleansing velocity
B. Less than the self-cleansing velocity
C. Less than 10 m/sec
D. More than 20 m/sec
A. A gap of 7.5 cm between the bottom of the covering slab and the top level of scum is provided
B. The outlet invert level is kept 5 to 7.5 cm below the inlet invert level
C. The minimum width of septic level is 90 cm
D. The depth of tank is kept equal to its width