Economic saving of time results by crashing_________________?
		A. cheapest critical activity
B. cheapest non-critical activity
C. costliest critical activity
D. costliest non-critical activity
		A. cheapest critical activity
B. cheapest non-critical activity
C. costliest critical activity
D. costliest non-critical activity
		A. 9 days
B. 13 days
C. 14 days
D. 19 days
		(i) Output can be increased by reducing the angle of swing for a given depth of cut
(ii) For a given angle of swing, output will be maximum at optimum depth of cut
(iii) Output can be increased by keeg the depth of cut less than optimum depth
(iv) Output can be increased by increasing the size of shovel
select the correct statements?
A. (ii), (iii) and (iv) are correct
B. (i), (ii) and (iv) are correct
C. (i), (iii) and (iv) are correct
D. (i) and (iv) are correct
		A. resource levelling
B. resource smoothening
C. updating
D. critical path scheduling
		A. interdependencies of activities
B. project progress
C. uncertainties
D. all of the above
		A. Hoe
B. Shovel
C. Dragline
D. None of the above
		Consider the following operations :
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
A. 1,2,4,3,5
B. 1,3,2,4,5
C. 1,2,3,4,5
D. 1,3,4,2,5