Critical path_____________?
Critical path_____________?
A. is always longest
B. is always shortest
C. may be longest
D. may be shortest
A. is always longest
B. is always shortest
C. may be longest
D. may be shortest
A. 9 days
B. 13 days
C. 14 days
D. 19 days
A. 10000 kg
B. 12500 kg
C. 22500 kg
D. 5000 kg
A. 4 days
B. 6 days
C. 10 days
D. 16 days
A. total duration of project is reduced
B. total duration of project is increased
C. uniform demand of resources is achieved
D. cost of project is controlled
A. Both A and R are true and R is the correct explanation of A
B. Both A and R are true but R is not the correct explanation of A
C. A is true but R is false
D. A is false but R is true
A. total float and free float
B. total float and independent float
C. free float and independent float
D. none of the above