Time And Work

A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?

Question:
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?

[A].

Rs. 375

[B].

Rs. 400

[C].

Rs. 600

[D].

Rs. 800

Answer: Option B

Explanation:

C’s 1 day’s work = 1 1 + 1 = 1 7 = 1 .
3 6 8 3 24 24
A’s wages : B’s wages : C’s wages = 1 : 1 : 1 = 4 : 3 : 1.
6 8 24
C’s share (for 3 days) = Rs. 3 x 1 x 3200 = Rs. 400.
24

A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C? Read More »

Aptitude, Time And Work

A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

Question:
A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

[A].

30 days

[B].

40 days

[C].

60 days

[D].

70 days

Answer: Option C

Explanation:

Let A’s 1 day’s work = x and B’s 1 day’s work = y.

Then, x + y = 1 and 16x + 44y = 1.
30
Solving these two equations, we get: x = 1 and y = 1
60 60
B’s 1 day’s work = 1 .
60

Hence, B alone shall finish the whole work in 60 days.

A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone? Read More »

Aptitude, Time And Work

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

Question:
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

[A].

6 days

[B].

10 days

[C].

15 days

[D].

20 days

Answer: Option B

Explanation:

Work done by X in 4 days = 1 x 4 = 1 .
20 5
Remaining work = 1 – 1 = 4 .
5 5
(X + Y)’s 1 day’s work = 1 + 1 = 8 = 2 .
20 12 60 15
Now, 2 work is done by X and Y in 1 day.
15
So, 4 work will be done by X and Y in 15 x 4 = 6 days.
5 2 5

Hence, total time taken = (6 + 4) days = 10 days.

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last? Read More »

Aptitude, Time And Work

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

Question:
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

[A].

5 days

[B].

6 days

[C].

10 days

[D].

10 1 days
2

Answer: Option C

Explanation:

(B + C)’s 1 day’s work = 1 + 1 = 7 .
9 12 36
Work done by B and C in 3 days = 7 x 3 = 7 .
36 12
Remaining work = 1 – 7 = 5 .
12 12
Now, 1 work is done by A in 1 day.
24
So, 5 work is done by A in 24 x 5 = 10 days.
12 12

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in: Read More »

Aptitude, Time And Work

Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:

Question:
Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:

[A].

15

[B].

16

[C].

18

[D].

25

Answer: Option B

Explanation:

Ratio of times taken by Sakshi and Tanya = 125 : 100 = 5 : 4.

Suppose Tanya takes x days to do the work.

5 : 4 :: 20 : x    x = 4 x 20
5

x = 16 days.

Hence, Tanya takes 16 days to complete the work.

Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is: Read More »

Aptitude, Time And Work

A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

Question: A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

[A].

20 days

[B].

22 1 days
2

[C].

25 days

[D].

30 days

Answer: Option B

Explanation:

Ratio of times taken by A and B = 1 : 3.

The time difference is (3 – 1) 2 days while B take 3 days and A takes 1 day.

If difference of time is 2 days, B takes 3 days.

If difference of time is 60 days, B takes 3 x 60 = 90 days.
2

So, A takes 30 days to do the work.

A’s 1 day’s work = 1
30
B’s 1 day’s work = 1
90
(A + B)’s 1 day’s work = 1 + 1 = 4 = 2
30 90 90 45
A and B together can do the work in 45 = 22 1 days.
2 2

A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in: Read More »

Aptitude, Time And Work

A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:

Question:
A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:

[A].

15 days

[B].

20 days

[C].

25 days

[D].

30 days

Answer: Option C

Explanation:

(A + B)’s 1 day’s work = 1
10
C’s 1 day’s work = 1
50
(A + B + C)’s 1 day’s work = 1 + 1 = 6 = 3 . …. (i)
10 50 50 25

A’s 1 day’s work = (B + C)’s 1 day’s work …. (ii)

From (i) and (ii), we get: 2 x (A’s 1 day’s work) = 3
25
A’s 1 day’s work = 3 .
50
B’s 1 day’s work 1 3 = 2 = 1 .
10 50 50 25

So, B alone could do the work in 25 days.

A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in: Read More »

Aptitude, Time And Work

P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?

Question:
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?

[A].

5 5
11

[B].

5 6
11

[C].

6 5
11

[D].

6 6
11

Answer: Option A

Explanation:

P can complete the work in (12 x 8) hrs. = 96 hrs.

Q can complete the work in (8 x 10) hrs. = 80 hrs.

P’s1 hour’s work = 1 and Q’s 1 hour’s work = 1 .
96 80
(P + Q)’s 1 hour’s work = 1 + 1 = 11 .
96 80 480
So, both P and Q will finish the work in 480 hrs.
11
Number of days of 8 hours each = 480 x 1 = 60 days = 5 5 days.
11 8 11 11

P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work? Read More »

Aptitude, Time And Work

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:

Question: A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:

[A].

4 days

[B].

6 days

[C].

8 days

[D].

12 days

Answer: Option B

Explanation:

Suppose A, B and C take x, x and x days respectively to finish the work.
2 3
Then, 1 + 2 + 3 = 1
x x x 2
6 = 1
x 2

x = 12.

So, B takes (12/2) = 6 days to finish the work.

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in: Read More »

Aptitude, Time And Work

A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in:

Question:
A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in:

[A].

1 day
24

[B].

7 day
24

[C].

3 3 days
7

[D].

4 days

Answer: Option C

Explanation:

Formula: If A can do a piece of work in n days, then A’s 1 day’s work = 1 .
n
(A + B + C)’s 1 day’s work = 1 + 1 + 1 = 7 .
24 6 12 24
Formula: If A’s 1 day’s work = 1 , then A can finish the work in n days.
n
So, all the three together will complete the job in 24 days = 3 3 days.
7 7

A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in: Read More »

Aptitude, Time And Work