Railway Engineering

When semaphore and warner are installed on the same post, then the stop indication is given when___________________?

When semaphore and warner are installed on the same post, then the stop indication is given when___________________?

A. both arms are horizontal
B. semaphore arm lowered but warner arm horizontal
C. both semaphore and warner arms lowered
D. none of the above

When semaphore and warner are installed on the same post, then the stop indication is given when___________________? Read More »

Railway Engineering

Which of the following statements regarding ballast materials are correct ?

Which of the following statements regarding ballast materials are correct ?

A. Brick ballast has poor drainage characteristics.
B. Coal ash is not used as ballast with steel or cast iron sleepers.
C. Gravel ballast gives better performance on soft formation.
D. Sand ballast causes excessive wear on top of rail

Which of the following statements regarding ballast materials are correct ? Read More »

Railway Engineering

Consider the following statements about concrete sleepers_________________?

Consider the following statements about concrete sleepers_________________?

1. They improve the track modulus.
2. They have good scrap value.
3. They render transportation easy.
4. They maintain the gauge quite satisfactorily.Of these statements

A. 1 and 2 are correct
B. 2 and 3 are correct
C. 3 and 4 are correct
D. 1 and 4 are correct

Consider the following statements about concrete sleepers_________________? Read More »

Railway Engineering

A train is hauled by 2-8-2 locomotive with 22.5 tonnes and on each driving axle. Assuming the coefficient of rail-wheel friction to be 0.25, what would be the hauling capacity of the locomotive?

A train is hauled by 2-8-2 locomotive with 22.5 tonnes and on each driving axle. Assuming the coefficient of rail-wheel friction to be 0.25, what would be the hauling capacity of the locomotive?

A. 15.0 tonnes
B. 22.5 tonnes
C. 45.0 tonnes
D. 90.0 tonnes

A train is hauled by 2-8-2 locomotive with 22.5 tonnes and on each driving axle. Assuming the coefficient of rail-wheel friction to be 0.25, what would be the hauling capacity of the locomotive? Read More »

Railway Engineering

For a sleeper density of (n+5), the number of sleepers required for constructing a broad gauge railway track of length 650 m is____________________?

For a sleeper density of (n+5), the number of sleepers required for constructing a broad gauge railway track of length 650 m is____________________?

A. 975
B. 918
C. 900
D. 880

For a sleeper density of (n+5), the number of sleepers required for constructing a broad gauge railway track of length 650 m is____________________? Read More »

Railway Engineering