A milestone chart_______________________?

A milestone chart_______________________?

A. shows the inter dependences of various jobs
B. depicts the delay of jobs, if any
C. points outgoing ahead of schedule of jobs, if any
D. all of the above
E. none of the above

The basic difference between PERT and CPM is that_____________?

The basic difference between PERT and CPM is that_____________?

A. PERT deals with events and CPM with activities
B. critical path is determined in PERT only
C. costs are considered on CPM only and not in PERT
D. guessed times are used in PERT and evaluated times in CPM
E. PERT is used in workshops and CPM in plants

Slack represents the difference between the___________________?

Slack represents the difference between the___________________?

A. latest allowable time and the normal expected time
B. latest allowable time and the earliest expected time
C. proposed allowable time and the earliest expected time
D. normal allowable time and the latest expected time
E. project initiation tune and actual starting time

String diagram is used_________________?

String diagram is used_________________?

A. for checking the relative values of various layouts
B. when a group of workers are working at a place
C. where processes require the operator to be moved from one place to another
D. all of the above
E. none of the above