Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?

Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?

A. latest start time of succeeding event -earliest finish time of preceding event activity time
B. latest start time of the event – earliest start time of the event
C. latest finish time of event – earliest finish time of the event
D. anyone of the above
E. none of the above

Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________? Read More »

Production Technology

Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it_________________?

Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it_________________?

A. consumes time, but no resources
B. consumes resources but no time
C. consumes neither time nor resources
D. is a dangling event
E. consumes both resources and time

Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it_________________? Read More »

Production Technology

Pick up the incorrect statement from the following. A critical ratio scheduling____________________?

Pick up the incorrect statement from the following. A critical ratio scheduling____________________?

A. establishes the relative priorities among various activities on a common basis
B. determines the status of each activity
C. adjusts automatically changes in activity progress
D. is a dynamic system
E. none of the above

Pick up the incorrect statement from the following. A critical ratio scheduling____________________? Read More »