The act of going round the production shop to note down the progress of work andfeedback the information is known as:

Question:

The act of going round the production shop to note down the progress of work andfeedback the information is known as:

A.

Follow up

B.

Dispatching

C.

Routing

D.

Trip card

Answer» a. Follow up

Note: The above multiple-choice question is for all general and Competitive Exams in India

In a network diagram, the activity that must be completed prior to the start of anactivity is called as

Question:

In a network diagram, the activity that must be completed prior to the start of anactivity is called as

A.

Successor activity

B.

Predecessor activity

C.

Concurrent activity

D.

Dummy activity

Answer» b. Predecessor activity

Note: The above multiple-choice question is for all general and Competitive Exams in India

One of the requirements of Aggregate Planning is:

Question:

One of the requirements of Aggregate Planning is:

A.

Both output and sales should be expressed in a logical overall unit of measuring

B.

Appropriate time period

C.

List of all resources available

D.

List of operations required.

Answer» a. Both output and sales should be expressed in a logical overall unit of measuring

Note: The above multiple-choice question is for all general and Competitive Exams in India