» Operations Management and Strategic Management solved MCQs

Line of Best fit is another name given to:

Question:

Line of Best fit is another name given to:

A.

Method of Least Squares

B.

Moving average method

C.

Semi average method

D.

Trend line method

Answer» a. Method of Least Squares

Note: The above multiple-choice question is for all general and Competitive Exams in India

Line of Best fit is another name given to: Read More »

» Operations Management and Strategic Management solved MCQs

Conducting occasional check-ups of the products manufactured or assembled toensure high quality of the production is known as:

Question:

Conducting occasional check-ups of the products manufactured or assembled toensure high quality of the production is known as:

A.

Planning

B.

Scheduling

C.

Inspection

D.

Routing

Answer» c. Inspection

Note: The above multiple-choice question is for all general and Competitive Exams in India

Conducting occasional check-ups of the products manufactured or assembled toensure high quality of the production is known as: Read More »

» Operations Management and Strategic Management solved MCQs

Most important benefit to the consumer from efficient production system is:

Question:

Most important benefit to the consumer from efficient production system is:

A.

He can save money

B.

He will have product of his choice easily available

C.

He gets increased use value in the product

D.

He can get the product on credit.

Answer» c. He gets increased use value in the product

Note: The above multiple-choice question is for all general and Competitive Exams in India

Most important benefit to the consumer from efficient production system is: Read More »

» Operations Management and Strategic Management solved MCQs

In Continuous manufacturing system, we need:

Question:

In Continuous manufacturing system, we need:

A.

General purpose machines and Skilled labours

B.

Special machine tools and highly skilled labours

C.

Semi automatic machines and unskilled labours

D.

General purpose machines and unskilled labours.

Answer» b. Special machine tools and highly skilled labours

Note: The above multiple-choice question is for all general and Competitive Exams in India

In Continuous manufacturing system, we need: Read More »

» Operations Management and Strategic Management solved MCQs

Number of product varieties that can be manufactured in Job production is:

Question:

Number of product varieties that can be manufactured in Job production is:

A.

Limited to one or two

B.

Large varieties of products

C.

One only

D.

None of the above.

Answer» b. Large varieties of products

Note: The above multiple-choice question is for all general and Competitive Exams in India

Number of product varieties that can be manufactured in Job production is: Read More »

» Operations Management and Strategic Management solved MCQs

One of the important charts used in programme control is:

Question:

One of the important charts used in programme control is:

A.

Material chart

B.

Gantt chart

C.

Route chart

D.

Inspection chart

Answer» b. Gantt chart

Note: The above multiple-choice question is for all general and Competitive Exams in India

One of the important charts used in programme control is: Read More »

» Operations Management and Strategic Management solved MCQs

In Process Planning we plan:

Question:

In Process Planning we plan:

A.

Different machines required

B.

Different operations required

C.

We plan the flow of material in each department

D.

We design the product.

Answer» c. We plan the flow of material in each department

Note: The above multiple-choice question is for all general and Competitive Exams in India

In Process Planning we plan: Read More »

» Operations Management and Strategic Management solved MCQs

In which of the following stages the management should try to change its approachby changing its strategy from “buy my product” to “try my product”?

Question:

In which of the following stages the management should try to change its approachby changing its strategy from “buy my product” to “try my product”?

A.

Introduction

B.

Growth

C.

Maturity

D.

Decline

Answer» b. Growth

Note: The above multiple-choice question is for all general and Competitive Exams in India

In which of the following stages the management should try to change its approachby changing its strategy from “buy my product” to “try my product”? Read More »

» Operations Management and Strategic Management solved MCQs

The difference between product system and project system is:

Question:

The difference between product system and project system is:

A.

Project system the equipment and machinery are fixed where as in product system they are movable

B.

In Product system the machinery and equipment are fixed and in project system they are not fixed

C.

Project system produces only standardized products and product system produces only unstandardised products

D.

Products cannot be stocked whereas projects can be stocked.

Answer» b. In Product system the machinery and equipment are fixed and in project system they are not fixed

Note: The above multiple-choice question is for all general and Competitive Exams in India

The difference between product system and project system is: Read More »

» Operations Management and Strategic Management solved MCQs