Final stage of production planning, where production activities are coordinated andprojected on a time scale is known as:

Question:

Final stage of production planning, where production activities are coordinated andprojected on a time scale is known as:

A.

Scheduling

B.

Loading

C.

Expediting

D.

Routing

Answer» a. Scheduling

Note: The above multiple-choice question is for all general and Competitive Exams in India

The way in which we can assess the efficiency of the production plant is by:

Question:

The way in which we can assess the efficiency of the production plant is by:

A.

Efficient dispatching

B.

By manufacturing a good product

C.

By comparing the actual performance with targets specified in the specified programme

D.

By efficient production planning.

Answer» c. By comparing the actual performance with targets specified in the specified programme

Note: The above multiple-choice question is for all general and Competitive Exams in India

Z-chart can be used to show:

Question:

Z-chart can be used to show:

A.

Process used in production

B.

Quality level of the product

C.

Both the plan and the performance, and deviation from the plan

D.

To show cost structure of the product.

Answer» c. Both the plan and the performance, and deviation from the plan

Note: The above multiple-choice question is for all general and Competitive Exams in India

With reference to Aggregate Planning, identify which of the following statements is NOT correct?

Question:

With reference to Aggregate Planning, identify which of the following statements is NOT correct?

A.

It is an Intermediate-term planning.

B.

It is made operational through a master schedule, which gives the manufacturing schedule.

C.

Facility planning and scheduling are closely related with the aggregate planning.

D.

It deals with the strategic decisions, such as purchase of facilities, introduction of new products, processes, etc.

Answer» d. It deals with the strategic decisions, such as purchase of facilities, introduction of new products, processes, etc.

Note: The above multiple-choice question is for all general and Competitive Exams in India

Issuing necessary orders, and taking necessary steps to ensure that the time targetsset in the schedules are effectively achieved is known as:

Question:

Issuing necessary orders, and taking necessary steps to ensure that the time targetsset in the schedules are effectively achieved is known as:

A.

Routing

B.

Dispatching

C.

Scheduling

D.

Inspection.

Answer» b. Dispatching