Updating may result in_________________?
Updating may result in_________________? A. change of critical path B. decrease of project completion time C. increase of project completion timeD. all of the above
Updating may result in_________________? A. change of critical path B. decrease of project completion time C. increase of project completion timeD. all of the above
The normal time required for the completion of project in the above problem is_______________? A. 9 days B. 13 daysC. 14 days D. 19 days
The process of incorporating changes and rescheduling or replanning is called_______________? A. resource levelling B. resource smootheningC. updating D. critical path scheduling
The reduction in project time normally results in_______________? A. decreasing the direct cost and increasing indirect costB. increasing the direct cost and decreasing the indirect cost C. increasing the direct cost and indirect cost both D. decreasing the direct cost…
The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as_______________? A. total float B. free float C. interfering floatD. independent float
A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other…
Critical path_____________? A. is always longest B. is always shortest C. may be longest D. may be shortest
Whenever an activity has zero total float, then_______________? A. free float of the activity must be zero but independent float need not be zero B. independent float must be zero but free float need not be zeroC. free float and…
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then______________? A. expected time of activity A is greater than the…
Latest start of an activity is always________________? A. greater than or equal to latest event time of preceding node B. less than or equal to latest event time of preceding node C. equal to latest event time of preceding node…