The minimum width of the fire escape stairs shall be?
A. 1.00 m
B. 1.25 m
C. 1.5 m
D. 2.0 m
The minimum width of the fire escape stairs shall be? Read More »
Construction Planning and ManagementA. 1.00 m
B. 1.25 m
C. 1.5 m
D. 2.0 m
The minimum width of the fire escape stairs shall be? Read More »
Construction Planning and Management A. small projects
B. large and complex projects
C. research and development projects
D. deterministic activities
PERT technique of network analysis is mainly useful for__________________? Read More »
Construction Planning and Management A. normal distribution curve
B. Poisson’s distribution curve
C. Beta – distribution curve
D. none of the above
A. greater than earliest event time of the following node
B. less than earliest event time of the following node
C. less than or equal to earliest event time of the following node
D. greater than or equal to earliest event time of the following node
Earliest finish of an activity is always_______________? Read More »
Construction Planning and Management A. 2
B. 4
C. 8
D. 7
A. 3.5 and 5/6
B. 5 and 25/36
C. 3.5 and 25/36
D. 4 and 5/6
A. identify the activities which can be delayed without affecting the total float of preceding activity
B. identify the activities, which can be delayed without affecting the total float of succeeding activity
C. establish priorities
D. identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Free float is mainly used to_________________? Read More »
Construction Planning and Management A. its latest finish time and earliest start time for its successor activity
B. its latest start time and earliest start time
C. its latest start time and earliest finish time
D. its earliest finish time and earliest start time for its successor activity
Total float for any activity is defined as the difference between________________? Read More »
Construction Planning and Management A. its earliest finish time and earliest start time for its successor activity
B. its latest start time and earliest start time
C. its latest finish time and earliest start time for its successor activity
D. its earliest finish time and latest start time for its successor activity
Free float for any activity is defined as the difference between__________________? Read More »
Construction Planning and Management A. preceding activities
B. succeeding activities
C. the particular activity involved
D. none of the above
The independent float affects only_______________? Read More »
Construction Planning and Management