The first stage of neutral process of sludge digestion, is__________________?

August 15, 2021January 22, 2019 by admin
The first stage of neutral process of sludge digestion, is__________________?

A. Acid fermentation
B. Acid regressio
C. Alkaline fermentation
D. None of these

Categories Civil Engineering Mcqs, Waste Water Engineering

The self-cleansing velocity of water flowing through pipe lines, is___________________ ?

August 15, 2021January 22, 2019 by admin
The self-cleansing velocity of water flowing through pipe lines, is___________________ ?

A. 2 metres/sec
B. 1 metre/sec
C. 0.5 metre/sec
D. 0.25 metre/sec

Categories Civil Engineering Mcqs, Waste Water Engineering

In very first stage of decomposition of the organic matter in sewage________________?

August 15, 2021January 22, 2019 by admin
In very first stage of decomposition of the organic matter in sewage________________?

A. Nitrites are formed
B. Nitrates are formed
C. Carbondioxide is formed
D. Ammonia is formed

Categories Civil Engineering Mcqs, Waste Water Engineering

Design period of 40 to 50 years is adopted for_________________?

August 15, 2021January 22, 2019 by admin
Design period of 40 to 50 years is adopted for_________________?

A. Branch sewers
B. Main sewers
C. Trunk sewers
D. All the above

Categories Civil Engineering Mcqs, Waste Water Engineering

The disintegrating pump in which solid matter is broken up before passing out, is__________________?

August 15, 2021January 22, 2019 by admin
The disintegrating pump in which solid matter is broken up before passing out, is__________________?

A. Centrifugal pump
B. Reciprocating pump
C. Pneumatic ejector
D. None of these

Categories Civil Engineering Mcqs, Waste Water Engineering

The design period in years for pumping plants, is___________________?

August 15, 2021January 22, 2019 by admin
The design period in years for pumg plants, is___________________?

A. 1
B. 2 to 3
C. 3 to 5
D. 5 to 10

Categories Civil Engineering Mcqs, Waste Water Engineering

A manhole is generally provided at each__________________?

August 15, 2021January 22, 2019 by admin
A manhole is generally provided at each__________________?

A. Bend
B. Junction
C. Change of gradient
D. All the above

Categories Civil Engineering Mcqs, Waste Water Engineering

A nuisance is experienced in diluting water if dilution factor is less than_________________?

August 15, 2021January 22, 2019 by admin
A nuisance is experienced in diluting water if dilution factor is less than_________________?

A. 100
B. 60
C. 40
D. 20

Categories Civil Engineering Mcqs, Waste Water Engineering

If the side of a square sewer is 1000 mm, the diameter of a hydraulically equivalent circular section, is___________________?

August 15, 2021January 22, 2019 by admin
If the side of a square sewer is 1000 mm, the diameter of a hydraulically equivalent circular section, is___________________?

A. 1045 mm
B. 1065 mm
C. 1075 mm
D. 1095 mm

Categories Civil Engineering Mcqs, Waste Water Engineering

In detritus tanks______________________?

August 15, 2021January 22, 2019 by admin
In detritus tanks______________________?

A. Flow velocity is kept 0.09 m/sec
B. Detention period is kept 3 to 4 minutes
C. Organic and inorganic materials are separated
D. All the above