Our website is made possible by displaying online advertisements to our visitors. Please consider supporting us by whitelisting our website.

Aptitude

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

Question:
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

[A].

6 days

[B].

10 days

[C].

15 days

[D].

20 days

Answer: Option B

Explanation:

Work done by X in 4 days = 1 x 4 = 1 .
20 5
Remaining work = 1 – 1 = 4 .
5 5
(X + Y)’s 1 day’s work = 1 + 1 = 8 = 2 .
20 12 60 15
Now, 2 work is done by X and Y in 1 day.
15
So, 4 work will be done by X and Y in 15 x 4 = 6 days.
5 2 5

Hence, total time taken = (6 + 4) days = 10 days.

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last? Read More »

Aptitude, Time And Work

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

Question:
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

[A].

5 days

[B].

6 days

[C].

10 days

[D].

10 1 days
2

Answer: Option C

Explanation:

(B + C)’s 1 day’s work = 1 + 1 = 7 .
9 12 36
Work done by B and C in 3 days = 7 x 3 = 7 .
36 12
Remaining work = 1 – 7 = 5 .
12 12
Now, 1 work is done by A in 1 day.
24
So, 5 work is done by A in 24 x 5 = 10 days.
12 12

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in: Read More »

Aptitude, Time And Work

Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:

Question:
Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:

[A].

15

[B].

16

[C].

18

[D].

25

Answer: Option B

Explanation:

Ratio of times taken by Sakshi and Tanya = 125 : 100 = 5 : 4.

Suppose Tanya takes x days to do the work.

5 : 4 :: 20 : x    x = 4 x 20
5

x = 16 days.

Hence, Tanya takes 16 days to complete the work.

Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is: Read More »

Aptitude, Time And Work

A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

Question: A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

[A].

20 days

[B].

22 1 days
2

[C].

25 days

[D].

30 days

Answer: Option B

Explanation:

Ratio of times taken by A and B = 1 : 3.

The time difference is (3 – 1) 2 days while B take 3 days and A takes 1 day.

If difference of time is 2 days, B takes 3 days.

If difference of time is 60 days, B takes 3 x 60 = 90 days.
2

So, A takes 30 days to do the work.

A’s 1 day’s work = 1
30
B’s 1 day’s work = 1
90
(A + B)’s 1 day’s work = 1 + 1 = 4 = 2
30 90 90 45
A and B together can do the work in 45 = 22 1 days.
2 2

A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in: Read More »

Aptitude, Time And Work

A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:

Question:
A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:

[A].

15 days

[B].

20 days

[C].

25 days

[D].

30 days

Answer: Option C

Explanation:

(A + B)’s 1 day’s work = 1
10
C’s 1 day’s work = 1
50
(A + B + C)’s 1 day’s work = 1 + 1 = 6 = 3 . …. (i)
10 50 50 25

A’s 1 day’s work = (B + C)’s 1 day’s work …. (ii)

From (i) and (ii), we get: 2 x (A’s 1 day’s work) = 3
25
A’s 1 day’s work = 3 .
50
B’s 1 day’s work 1 3 = 2 = 1 .
10 50 50 25

So, B alone could do the work in 25 days.

A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in: Read More »

Aptitude, Time And Work

P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?

Question:
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?

[A].

5 5
11

[B].

5 6
11

[C].

6 5
11

[D].

6 6
11

Answer: Option A

Explanation:

P can complete the work in (12 x 8) hrs. = 96 hrs.

Q can complete the work in (8 x 10) hrs. = 80 hrs.

P’s1 hour’s work = 1 and Q’s 1 hour’s work = 1 .
96 80
(P + Q)’s 1 hour’s work = 1 + 1 = 11 .
96 80 480
So, both P and Q will finish the work in 480 hrs.
11
Number of days of 8 hours each = 480 x 1 = 60 days = 5 5 days.
11 8 11 11

P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work? Read More »

Aptitude, Time And Work

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:

Question: A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:

[A].

4 days

[B].

6 days

[C].

8 days

[D].

12 days

Answer: Option B

Explanation:

Suppose A, B and C take x, x and x days respectively to finish the work.
2 3
Then, 1 + 2 + 3 = 1
x x x 2
6 = 1
x 2

x = 12.

So, B takes (12/2) = 6 days to finish the work.

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in: Read More »

Aptitude, Time And Work

A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in:

Question:
A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in:

[A].

1 day
24

[B].

7 day
24

[C].

3 3 days
7

[D].

4 days

Answer: Option C

Explanation:

Formula: If A can do a piece of work in n days, then A’s 1 day’s work = 1 .
n
(A + B + C)’s 1 day’s work = 1 + 1 + 1 = 7 .
24 6 12 24
Formula: If A’s 1 day’s work = 1 , then A can finish the work in n days.
n
So, all the three together will complete the job in 24 days = 3 3 days.
7 7

A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in: Read More »

Aptitude, Time And Work

It takes eight hours for a 600 km journey, if 120 km is done by train and the rest by car. It takes 20 minutes more, if 200 km is done by train and the rest by car. The ratio of the speed of the train to that of the cars is:

Question:
It takes eight hours for a 600 km journey, if 120 km is done by train and the rest by car. It takes 20 minutes more, if 200 km is done by train and the rest by car. The ratio of the speed of the train to that of the cars is:

[A].

2 : 3

[B].

3 : 2

[C].

3 : 4

[D].

4 : 3

Answer: Option C

Explanation:

Let the speed of the train be x km/hr and that of the car be y km/hr.

Then, 120 + 480 = 8       1 + 4 = 1 ….(i)
x y x y 15
And, 200 + 400 = 25     1 + 2 = 1 ….(ii)
x y 3 x y 24

Solving (i) and (ii), we get: x = 60 and y = 80.

Ratio of speeds = 60 : 80 = 3 : 4.

It takes eight hours for a 600 km journey, if 120 km is done by train and the rest by car. It takes 20 minutes more, if 200 km is done by train and the rest by car. The ratio of the speed of the train to that of the cars is: Read More »

Aptitude, Time And Distance

In a flight of 600 km, an aircraft was slowed down due to bad weather. Its average speed for the trip was reduced by 200 km/hr and the time of flight increased by 30 minutes. The duration of the flight is:

Question:
In a flight of 600 km, an aircraft was slowed down due to bad weather. Its average speed for the trip was reduced by 200 km/hr and the time of flight increased by 30 minutes. The duration of the flight is:

[A].

1 hour

[B].

2 hours

[C].

3 hours

[D].

4 hours

Answer: Option A

Explanation:

Let the duration of the flight be x hours.

Then, 600 600 = 200
x x + (1/2)
600 1200 = 200
x 2x + 1

x(2x + 1) = 3

2×2 + x – 3 = 0

(2x + 3)(x – 1) = 0

x = 1 hr.      [neglecting the -ve value of x]

In a flight of 600 km, an aircraft was slowed down due to bad weather. Its average speed for the trip was reduced by 200 km/hr and the time of flight increased by 30 minutes. The duration of the flight is: Read More »

Aptitude, Time And Distance