Our website is made possible by displaying online advertisements to our visitors. Please consider supporting us by whitelisting our website.

Aptitude

A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?

Question: A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?
[A].

40

[B].

50

[C].

54

[D].

60

Answer: Option D

Explanation:

(A + B)’s 20 day’s work = 1 x 20 = 2 .
30 3
Remaining work = 1 – 2 = 1 .
3 3
Now, 1 work is done by A in 20 days.
3

Therefore, the whole work will be done by A in (20 x 3) = 60 days.

A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work? Read More »

Aptitude, Time And Work

A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?

Question: A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?
[A].

18 days

[B].

24 days

[C].

30 days

[D].

36 days

Answer: Option A

Explanation:

2(A + B + C)’s 1 day’s work = 1 + 1 + 1 = 15 = 1 .
30 24 20 120 8
Therefore, (A + B + C)’s 1 day’s work = 1 = 1 .
2 x 8 16
Work done by A, B, C in 10 days = 10 = 5 .
16 8
Remaining work = 1 – 5 = 3 .
8 8
A’s 1 day’s work = 1 1 = 1 .
16 24 48
Now, 1 work is done by A in 1 day.
48
So, 3 work will be done by A in 48 x 3 = 18 days.
8 8

A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work? Read More »

Aptitude, Time And Work

A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?

Question: A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?
[A].

11:30 A.M.

[B].

12 noon

[C].

12:30 P.M.

[D].

1:00 P.M.

Answer: Option D

Explanation:

(P + Q + R)’s 1 hour’s work = 1 + 1 + 1 = 37 .
8 10 12 120
Work done by P, Q and R in 2 hours = 37 x 2 = 37 .
120 60
Remaining work = 1 – 37 = 23 .
60 60
(Q + R)’s 1 hour’s work = 1 + 1 = 11 .
10 12 60
Now, 11 work is done by Q and R in 1 hour.
60
So, 23 work will be done by Q and R in 60 x 23 = 23 hours 2 hours.
60 11 60 11

So, the work will be finished approximately 2 hours after 11 A.M., i.e., around 1 P.M.

A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ? Read More »

Aptitude, Time And Work

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :

Question: A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :
[A].

8 days

[B].

10 days

[C].

12 days

[D].

15 days

Answer: Option C

Explanation:

(A + B)’s 1 day’s work = 1 + 1 = 1 .
15 10 6
Work done by A and B in 2 days = 1 x 2 = 1 .
6 3
Remaining work = 1 – 1 = 2 .
3 3
Now, 1 work is done by A in 1 day.
15
2 work will be done by a in 15 x 2 = 10 days.
3 3

Hence, the total time taken = (10 + 2) = 12 days.

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in : Read More »

Aptitude, Time And Work

A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

Question: A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
[A].

5

[B].

5 1
2

[C].

6

[D].

8

Answer: Option C

Explanation:

B’s 10 day’s work = 1 x 10 = 2 .
15 3
Remaining work = 1 – 2 = 1 .
3 3
Now, 1 work is done by A in 1 day.
18
1 work is done by A in 18 x 1 = 6 days.
3 3

A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work? Read More »

Aptitude, Time And Work

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

Question: A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
[A].

1
4

[B].

1
10

[C].

7
15

[D].

8
15

Answer: Option D

Explanation:

A’s 1 day’s work = 1 ;
15
B’s 1 day’s work = 1 ;
20
(A + B)’s 1 day’s work = 1 + 1 = 7 .
15 20 60
(A + B)’s 4 day’s work = 7 x 4 = 7 .
60 15
Therefore, Remaining work = 1 – 7 = 8 .
15 15

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is : Read More »

Aptitude, Time And Work

A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?

Question: A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
[A].

11 days

[B].

13 days

[C].

20 3 days
17

[D].

None of these

Answer: Option B

Explanation:

Ratio of times taken by A and B = 100 : 130 = 10 : 13.

Suppose B takes x days to do the work.

Then, 10 : 13 :: 23 : x         x = 23 x 13         x = 299 .
10 10
A’s 1 day’s work = 1 ;
23
B’s 1 day’s work = 10 .
299
(A + B)’s 1 day’s work = 1 + 10 = 23 = 1 .
23 299 299 13

Therefore, A and B together can complete the work in 13 days.

A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days? Read More »

Aptitude, Time And Work

A and B can do a job together in 7 days. A is 1 times as efficient as B. The same job can be done by A alone in :

Question: A and B can do a job together in 7 days. A is 1 times as efficient as B. The same job can be done by A alone in :
[A].

9 1 days
3

[B].

11 days

[C].

12 1 days
4

[D].

16 1 days
3

Answer: Option B

Explanation:

(A’s 1 day’s work) : (B’s 1 day’s work) = 7 : 1   =   7 : 4.
4

Let A’s and B’s 1 day’s work be 7x and 4x respectively.

Then, 7x + 4x = 1         11x = 1         x = 1 .
7 7 77
A’s 1 day’s work = 1 x 7 = 1 .
77 11

A and B can do a job together in 7 days. A is 1 times as efficient as B. The same job can be done by A alone in : Read More »

Aptitude, Time And Work

A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :

Question: A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :
[A].

4 days

[B].

6 days

[C].

8 days

[D].

18 days

Answer: Option A

Explanation:

Ratio of rates of working of A and B = 2 : 1.

So, ratio of times taken = 1 : 2.

B’s 1 day’s work = 1 .
12
A’s 1 day’s work = 1 ; (2 times of B’s work)
6
(A + B)’s 1 day’s work = 1 + 1 = 3 = 1 .
6 12 12 4

So, A and B together can finish the work in 4 days.

A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in : Read More »

Aptitude, Time And Work

A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?

Question: A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
[A].

8 hours

[B].

10 hours

[C].

12 hours

[D].

24 hours

Answer: Option C

Explanation:

A’s 1 hour’s work = 1 ;
4
(B + C)’s 1 hour’s work = 1 ;
3
(A + C)’s 1 hour’s work = 1 .
2
(A + B + C)’s 1 hour’s work = 1 + 1 = 7 .
4 3 12
B’s 1 hour’s work = 7 1 = 1 .
12 2 12

B alone will take 12 hours to do the work.

A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it? Read More »

Aptitude, Time And Work