[A].
[B].
[C].
[D].
Answer: Option B
Explanation:
1 hectare = 10,000 m2
So, Area = (1.5 x 10000) m2 = 15000 m2.
| Depth = | 5 | m | = | 1 | m. |
| 100 | 20 |
| Volume = (Area x Depth) = | 15000 x | 1 | m3 | = 750 m3. | |
| 20 |
Video Explanation: https://youtu.be/dDbVuBzYop8
[B].
[C].
[D].
Answer: Option B
Explanation:
1 hectare = 10,000 m2
So, Area = (1.5 x 10000) m2 = 15000 m2.
| Depth = | 5 | m | = | 1 | m. |
| 100 | 20 |
| Volume = (Area x Depth) = | 15000 x | 1 | m3 | = 750 m3. | |
| 20 |
Video Explanation: https://youtu.be/dDbVuBzYop8
[B].
[C].
[D].
Answer: Option B
Explanation:
| Volume of water displaced | = (3 x 2 x 0.01) m3 |
| = 0.06 m3. |
| Mass of man | = Volume of water displaced x Density of water |
| = (0.06 x 1000) kg | |
| = 60 kg. |
[B].
[C].
[D].
Answer: Option A
Explanation:
| Area of the wet surface | = [2(lb + bh + lh) – lb] |
| = 2(bh + lh) + lb | |
| = [2 (4 x 1.25 + 6 x 1.25) + 6 x 4] m2 | |
| = 49 m2. |
| 16 | 2 | % |
| 3 |
[B].
| 14 | 1 | % |
| 2 |
[C].
| 13 | 1 | % |
| 3 |
[D].
Answer: Option A
Explanation:
| S.P. = 102% of Rs. 600 = | 102 | x 600 | = Rs. 612. | ||
| 100 |
Now, P.W. = Rs. 612 and sum = Rs. 688.50.
T.D. = Rs. (688.50 – 612) = Rs. 76.50.
Thus, S.I. on Rs. 612 for 9 months is Rs. 76.50.
| Rate = | 100 x 76.50 | % | = 16% | |
|
[B].
[C].
[D].
Answer: Option C
Explanation:
| Sum = | S.I. x T.D. | = | 85 x 80 | = Rs. 1360. |
| (S.I.) – (T.D.) | (85 – 80) |
[B].
| 13 | 1 | % |
| 3 |
[C].
[D].
Answer: Option C
Explanation:
P.W. = Rs. (2562 – 122) = Rs. 2440.
S.I. on Rs. 2440 for 4 months is Rs. 122.
| Rate = | 100 x 122 | % | = 15%. | |
|
[B].
[C].
[D].
Answer: Option A
Explanation:
| P.W. = | 100 x T.D. | = | 100 x 168 | = 600. |
| R x T | 14 x 2 |
Sum = (P.W. + T.D.) = Rs. (600 + 168) = Rs. 768.
[B].
[C].
[D].
Answer: Option B
Explanation:
| P.W. = Rs. | 100 x 2310 | = Rs. 1680. | ||||
|
[B].
[C].
[D].
Answer: Option C
Explanation:
| Whole work is done by A in | 20 x | 5 | = 25 days. | ||
| 4 |
| Now, | 1 – | 4 | i.e., | 1 | work is done by A and B in 3 days. | ||
| 5 | 5 |
Whole work will be done by A and B in (3 x 5) = 15 days.
| A’s 1 day’s work = | 1 | , (A + B)’s 1 day’s work = | 1 | . |
| 25 | 15 |
| B’s 1 day’s work = | 1 | – | 1 | = | 4 | = | 2 | . | ||
| 15 | 25 | 150 | 75 |
| So, B alone would do the work in | 75 | = 37 | 1 | days. |
| 2 | 2 |
| 13 | 1 | days |
| 3 |
[B].
[C].
[D].
Answer: Option A
Explanation:
| Work done by X in 8 days = | 1 | x 8 | = | 1 | . | ||
| 40 | 5 |
| Remaining work = | 1 – | 1 | = | 4 | . | ||
| 5 | 5 |
| Now, | 4 | work is done by Y in 16 days. |
| 5 |
| Whole work will be done by Y in | 16 x | 5 | = 20 days. | ||
| 4 |
| X’s 1 day’s work = | 1 | , Y’s 1 day’s work = | 1 | . |
| 40 | 20 |
| (X + Y)’s 1 day’s work = | 1 | + | 1 | = | 3 | . | ||
| 40 | 20 | 40 |
| Hence, X and Y will together complete the work in | 40 | = 13 | 1 | days. | ||
| 3 | 3 |