At which stage of risk analysis specification, the additional security requirements take account of the technologies used in building the system and system design and implementation decisions ?

At which stage of risk analysis specification, the additional security requirements take account of the technologies used in building the system and system design and implementation decisions ?

A. Preliminary risk analysis
B. Life-cycle risk analysis
C. Operational risk analysis
D. All of the mentioned

Explanation: This risk assessment takes place during the system development life cycle after design choices have been made..