Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?

Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?

A. latest start time of succeeding event -earliest finish time of preceding event activity time
B. latest start time of the event – earliest start time of the event
C. latest finish time of event – earliest finish time of the event
D. anyone of the above
E. none of the above