A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :

Question: A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :
[A].

4 days

[B].

6 days

[C].

8 days

[D].

18 days

Answer: Option A

Explanation:

Ratio of rates of working of A and B = 2 : 1.

So, ratio of times taken = 1 : 2.

B’s 1 day’s work = 1 .
12
A’s 1 day’s work = 1 ; (2 times of B’s work)
6
(A + B)’s 1 day’s work = 1 + 1 = 3 = 1 .
6 12 12 4

So, A and B together can finish the work in 4 days.