Question: A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
[A].
[A].
1 |
4 |
[B].
1 |
10 |
[C].
7 |
15 |
[D].
8 |
15 |
Answer: Option D
Explanation:
A’s 1 day’s work = | 1 | ; |
15 |
B’s 1 day’s work = | 1 | ; |
20 |
(A + B)’s 1 day’s work = | 1 | + | 1 | = | 7 | . | ||
15 | 20 | 60 |
(A + B)’s 4 day’s work = | 7 | x 4 | = | 7 | . | ||
60 | 15 |
Therefore, Remaining work = | 1 – | 7 | = | 8 | . | ||
15 | 15 |