Question: A and B can do a job together in 7 days. A is 1 times as efficient as B. The same job can be done by A alone in :
[A].
11 days
[A].
9 | 1 | days |
3 |
[B].
[C].
12 | 1 | days |
4 |
[D].
16 | 1 | days |
3 |
Answer: Option B
Explanation:
(A’s 1 day’s work) : (B’s 1 day’s work) = | 7 | : 1 = 7 : 4. |
4 |
Let A’s and B’s 1 day’s work be 7x and 4x respectively.
Then, 7x + 4x = | 1 | 11x = | 1 | x = | 1 | . |
7 | 7 | 77 |
A’s 1 day’s work = | 1 | x 7 | = | 1 | . | ||
77 | 11 |